Friday morning so the normal team have their morning off. A lot has been done in the 48 hours since we were last here. The big concrete run was done yesterday morning and marking out the ground storey interior has started. Also a very impreesive perimeter wall has been started. This will be 1.70m (about 5' 7'') high on the open road side. Ground zero inside he perimeter will be slightly higher than the roof of the pool pump room just below the back door. Although the ordinary staff get this morning off he same is not true for the sub-contractors. Therefore the roof constructors are hard at work preparing the wood as we walk around.